Following last Sunday's Operations Session on Cassino, I took the
opportunity to look at enhancing some things around the layout and then looked
at a couple of locos that might have had issues.
My Tillig dual gauge point at the northern end of Acacia
Ridge Yard always causes locos to stutter heading through it. When
running a consist this did not cause any issues, but when there is only a
single loco this can cause a complete stall. I cleaned the point blades
with methylated spirits and a cotton bud and soldered a joiner at the toe end
of the point to assist with electrical flow. The other end is made up of all insulated joiners as this
is the start of the next power district. I have since run a couple of standard gauge
locos through it in all directions and they all now performed well. I also ran
a couple of narrow gauge locos through the straight track and they also ran
well. Maybe I have fixed the issue.
Next stop was a point at the other end of Acacia Ridge Yard
in track 1. That particular point had bad electrical connectivity from the point
blades so I added a permanent jumper from the diverging rail to the straight
rail and now that works so much better after my tests.
Late on last Sunday I was testing the SX set hauled by the Golden
Holden and it just stopped short of the section where the mainline from Acacia
Ridge, the branch from Sunnybank and the lead into Rocklea Sidings all
diverge. A length of track that I installed for Sunnybank was second hand
and was as dirty as sin. So on Monday it was given a cleaning and then I ran my SX
set forward and back through this junction in all directions and performance
was satisfactory. That train has not travelled too much farther as the set is sitting in Clapham Yard.
I then tried to check out an Auscision loco - number 44236. It
stopped dead while Arthur was running No 19A on last Sunday. I could not
get it to move. But I did not try checking CV19 so see if it magically
joined a consist. I checked that later and that was not the cause. So it left me with
the only thing to do was to pull it apart and check the wires to the
motor. It looks like the motor is stuffed. I removed the motor and applied DC direct to the motor and it does not spin. I will have to try and
get a replacement motor from Auscision.
A scan of South Brisbane Interstate (SBI) Station on Monday showed
that it was in a complete mess. OMG! It was a complete cluster
… I had no idea where to start fixing up what was wrong. Well the
Sugar wagons should have been in Acacia Ridge Yard road 3, but were in SBI road
10. So I ran them back. The three wagons that should have been in
SBI road 10 were in SBI road 3. So I moved them into road 10.
Next step was to move the rest of the wagons in SBI road 3 into Park Road
Siding road 2. I noticed on Sunday that something was wrong with Park Road station, as I was supposed to do a shunt there and there was nothing in the yard. I was supposed to add my
train’s container wagons with those wagons in road 2 at Park Road Yard, but they were not
there. I think this was a left over from the last iteration of the
timetable and I did not pick this up earlier. But because of this train being at
South Brisbane, the driver of the Brisbane Limited could not put that train in
road 3 at SBI. So they put it in road 2. That was going to cause
all sorts of issues as SBI road 2 is used to run around all incoming trains in
SBI and that wasn’t going to occur with a train sitting in it.
So this took me about 3 hours to do, but I had fun. I
have since added quite a lot of detail to a number of Shunt Lists, to assist
crews in the future. I will spend some timeethis coming week working out where we are in the timetable for the next session. I might back track some trains.
One item that I forgot about from the Ops Session and it probably caused us one of the
most troublesome issues from the Ops Session was that the point from the Main
to the Yard in Cassino near the signal box had failed. I forgot to look
at this until late on Tuesday night when I remembered about the issue. On
Wednesday morning, I used my PROCAB-R handheld to throw the points in that
region individually. They all belong to a single DS64 point
controller. I started at address 421, 422 and 423 and they all worked.
Address 424 did not. Additionally, when I tried to enter this address the
DS64 did not respond. So it looked like that the DS64 had lost its
address in output 4. So I had to re-enter the addresses from 421 to 424
into the DS64. Once done, I entered 424 as the accessory number on the
PROCAB-R and sure enough it worked. This is one of the very, very few times
that I had lost an address in a DS64 point controller.
I have circled back to the Cassino Station Building. I
had previously found two SPDT switch to use in the controlling of the lights in
Cassino Station Building and the Refreshment Rooms. A third switch found
lying around will allow me to separately control the station master office
lights. This was wired up and tested and looks good.
The other week I
put my 3D printed DH, that I got from Barnacle, next to the Far North Model DH. The 3D printed
version with a motor chassis that I put together had the DH shell sitting very
high. I set about working on the chassis and removing some styrene.
After a short work period, the 3D version has come down by close to 5mm in height.
It is just a bit high, but so much better. I really need to get around in
making my other Far North Hobbies DH that I purchased a few years back now, as I have
a real working DH template to work from.
Saturday involved a
trip to Anthony’s place to act as the Station Master at Tatiara Downs for his Operations Session. I
worked with Alan as my shunter and Iain as West End. I have not been the
so called ‘Sheriff’ since the first few sessions I worked at Tatiara Downs. That is about 25 sessions ago. This is a stressful position. I think I struggled by and everything got
done. I forgot to swap a Guards van wagon card on one train, and 'The Real
Sheriff' (Brendan – who was out on the mainline running trains for a change)
chastised me as his train cards were in the wrong order. I just had it arranged
back to front instead of front to back. We had a great time in a
operating session lasting about 3 hr 10 minutes. I needed a rest after that session.