Following last Sunday's Operations Session on Cassino, I took the opportunity to look at enhancing some things around the layout and then looked at a couple of locos that might have had issues.
My Tillig dual gauge point at the northern end of Acacia Ridge Yard always causes locos to stutter heading through it. When running a consist this did not cause any issues, but when there is only a single loco this can cause a complete stall. I cleaned the point blades with methylated spirits and a cotton bud and soldered a joiner at the toe end of the point to assist with electrical flow. The other end is made up of all insulated joiners as this is the start of the next power district. I have since run a couple of standard gauge locos through it in all directions and they all now performed well. I also ran a couple of narrow gauge locos through the straight track and they also ran well. Maybe I have fixed the issue.
Next stop was a point at the other end of Acacia Ridge Yard in track 1. That particular point had bad electrical connectivity from the point blades so I added a permanent jumper from the diverging rail to the straight rail and now that works so much better after my tests.
Late on last Sunday I was testing the SX set hauled by the Golden Holden and it just stopped short of the section where the mainline from Acacia Ridge, the branch from Sunnybank and the lead into Rocklea Sidings all diverge. A length of track that I installed for Sunnybank was second hand and was as dirty as sin. So on Monday it was given a cleaning and then I ran my SX set forward and back through this junction in all directions and performance was satisfactory. That train has not travelled too much farther as the set is sitting in Clapham Yard.
I then tried to check out an Auscision loco - number 44236. It stopped dead while Arthur was running No 19A on last Sunday. I could not get it to move. But I did not try checking CV19 so see if it magically joined a consist. I checked that later and that was not the cause. So it left me with the only thing to do was to pull it apart and check the wires to the motor. It looks like the motor is stuffed. I removed the motor and applied DC direct to the motor and it does not spin. I will have to try and get a replacement motor from Auscision.
A scan of South Brisbane Interstate (SBI) Station on Monday showed that it was in a complete mess. OMG! It was a complete cluster … I had no idea where to start fixing up what was wrong. Well the Sugar wagons should have been in Acacia Ridge Yard road 3, but were in SBI road 10. So I ran them back. The three wagons that should have been in SBI road 10 were in SBI road 3. So I moved them into road 10. Next step was to move the rest of the wagons in SBI road 3 into Park Road Siding road 2. I noticed on Sunday that something was wrong with Park Road station, as I was supposed to do a shunt there and there was nothing in the yard. I was supposed to add my train’s container wagons with those wagons in road 2 at Park Road Yard, but they were not there. I think this was a left over from the last iteration of the timetable and I did not pick this up earlier. But because of this train being at South Brisbane, the driver of the Brisbane Limited could not put that train in road 3 at SBI. So they put it in road 2. That was going to cause all sorts of issues as SBI road 2 is used to run around all incoming trains in SBI and that wasn’t going to occur with a train sitting in it.
So this took me about 3 hours to do, but I had fun. I have since added quite a lot of detail to a number of Shunt Lists, to assist crews in the future. I will spend some timeethis coming week working out where we are in the timetable for the next session. I might back track some trains.
One item that I forgot about from the Ops Session and it probably caused us one of the most troublesome issues from the Ops Session was that the point from the Main to the Yard in Cassino near the signal box had failed. I forgot to look at this until late on Tuesday night when I remembered about the issue. On Wednesday morning, I used my PROCAB-R handheld to throw the points in that region individually. They all belong to a single DS64 point controller. I started at address 421, 422 and 423 and they all worked. Address 424 did not. Additionally, when I tried to enter this address the DS64 did not respond. So it looked like that the DS64 had lost its address in output 4. So I had to re-enter the addresses from 421 to 424 into the DS64. Once done, I entered 424 as the accessory number on the PROCAB-R and sure enough it worked. This is one of the very, very few times that I had lost an address in a DS64 point controller.
I have circled back to the Cassino Station Building. I had previously found two SPDT switch to use in the controlling of the lights in Cassino Station Building and the Refreshment Rooms. A third switch found lying around will allow me to separately control the station master office lights. This was wired up and tested and looks good.
The other week I put my 3D printed DH, that I got from Barnacle, next to the Far North Model DH. The 3D printed version with a motor chassis that I put together had the DH shell sitting very high. I set about working on the chassis and removing some styrene. After a short work period, the 3D version has come down by close to 5mm in height. It is just a bit high, but so much better. I really need to get around in making my other Far North Hobbies DH that I purchased a few years back now, as I have a real working DH template to work from.
Saturday involved a trip to Anthony’s place to act as the Station Master at Tatiara Downs for his Operations Session. I worked with Alan as my shunter and Iain as West End. I have not been the so called ‘Sheriff’ since the first few sessions I worked at Tatiara Downs. That is about 25 sessions ago. This is a stressful position. I think I struggled by and everything got done. I forgot to swap a Guards van wagon card on one train, and 'The Real Sheriff' (Brendan – who was out on the mainline running trains for a change) chastised me as his train cards were in the wrong order. I just had it arranged back to front instead of front to back. We had a great time in a operating session lasting about 3 hr 10 minutes. I needed a rest after that session.






















